Incepand de maine, 12 ianuarie 2016, va intra in vigoare noul examen de PMP care, conform declaratiilor reprezentantilor PMI, va contine intrebari noi in proportie de 25%.
Pe scurt, schimbarile se pare ca vin din incercarea PMI de a sublinia dinamica din ce in ce mai mare a mediului in care proiectele se desfasoara si ating prin intrebari, printre altele, urmatoarele zone:
- Alinierea proiectelor cu strategia de business
- Stakeholder Management
- Conectarea proiectelor cu organizatia prin: procesele de initiere ale proiectelor, imbunatatirea proceselor si valoarea lectiilor invatate
Mai in detaliu, o sinteza a schimbarilor oficiale poate fi consultata in urmatoarele doua post-uri:
Certificarea PMP® | O sinteza a schimbarilor oficiale din examenul de PMP 2016
Certificarea PMP® | Lista cu cele 8 taskuri noi din examenul de PMP 2016
Iata mai jos si un test de 20 de intrebari care adreseaza o parte din aceste schimbari anuntate de PMI.
Note:
1. Din momentul in care dati click pe “Start quiz” aveti 26 de minute si 40 de secunde pentru a finaliza testul.
2. Ca sa puteti rula testul va trebui sa aveti un user deja sau puteti sa va inregistrati acum si sa fiti logati.
3. Pentru a consulta raspunsurile corecte va trebui sa selectati dupa ce terminati testul optiunea:”View questions”
4. Pentru a afla rezultatul la test va trebui sa selectati “Finish Quiz”
5. Pentru discutii, comentarii sau debriefing Leave a reply
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
_________
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 20 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
| Average score |
|
| Your score |
|
Categories
- Not categorized 0%
-
Resurse noul examen de PMP 2016:
Certificarea PMP® | O sinteza a schimbarilor oficiale din examenul de PMP 2016
Certificarea PMP® | Lista cu cele 8 taskuri noi din examenul de PMP 2016
Pentru mai multe detalii sau daca doriti justificarea unui anumit raspuns Leave a reply
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Who should ensure a smooth transfer of the project’s deliverables into the business of the requesting organization after project closure?
Correct
The Sponsor – PMBOK Guide 5th Ed., pag. 32
Incorrect
The Sponsor – PMBOK Guide 5th Ed., pag. 32
-
Question 2 of 20
2. Question
Project success and deliverable acceptance criteria, process to align internal stakeholders with project process requirements and guidelines for aligning project governance and organizational strategy are all elements of:
Correct
Project governance framework – PMBOK Guide 5h Edition, pag. 34
Incorrect
Project governance framework – PMBOK Guide 5h Edition, pag. 34
-
Question 3 of 20
3. Question
You are the project manager for a project which is typical for your organization. The customer of the project is from the same domain as you are and knows the technology very well but has chose to outsource the project to your organization because of the time constraints. The contract between the customer and your organization for this project is firm fixed price. Reading the contract you noticed that there is no quality exit criteria specified for the deliverables of the contract but only a reference to a standard industry-specific. The success of the project should be measured in terms of completing the project within the constraints of:
Correct
Scope, time, cost, quality, resources, and risk as approved between the project manager and senior management – PMBOK Guide 5th Edition, pag. 35
Incorrect
Scope, time, cost, quality, resources, and risk as approved between the project manager and senior management – PMBOK Guide 5th Edition, pag. 35
-
Question 4 of 20
4. Question
You have coordinated the bidding activities for an opportunity which was won by your organization. One of the completed activities was a cost-benefit analysis. This is usually completed by:
Correct
A business analyst using various stakeholder inputs – PMBOK Guide 5th Edition, pag. 69
Incorrect
A business analyst using various stakeholder inputs – PMBOK Guide 5th Edition, pag. 69
-
Question 5 of 20
5. Question
You are the project manager for an internal project. The objective of this project is to automatize a Kanban approach for the order management process. Your feeling fed by your previous experience is that the functional manager who is currently responsible for the order management process will be resistant to this project. However, it is not for the first time when you have resistance stakeholders so you plan how to manage him and you document the strategy in the stakeholder management plan. The sponsor tells you that the stakeholder management plan as part of the project management plan should be open to all internal stakeholders. What is the BEST thing to do:
Correct
Tell the sponsor about the sensitive nature of the stakeholder management plan and explain him the potential damage of distributing this subsidiary plan to the resistant functional manager – PMBOK Guide 5th edition, pag. 404
Incorrect
Tell the sponsor about the sensitive nature of the stakeholder management plan and explain him the potential damage of distributing this subsidiary plan to the resistant functional manager – PMBOK Guide 5th edition, pag. 404
-
Question 6 of 20
6. Question
Modifying organizational behaviour to accept the project outcomes, facilitating consensus toward project objectives and negotiating agreements to satisfy the project need are all example of:
Correct
Management skills – PMBOK Guide 5th Edition, pag. 408
Incorrect
Management skills – PMBOK Guide 5th Edition, pag. 408
-
Question 7 of 20
7. Question
What do you need to manage stakeholder engagement?
Correct
Communication management plan and stakeholder management plan – PMBOK Guide 5th Edition, pag. 406
Incorrect
Communication management plan and stakeholder management plan – PMBOK Guide 5th Edition, pag. 406
-
Question 8 of 20
8. Question
Which of the following represents how the project manager should share the stakeholder management strategies:
Correct
PMBOK Guide 5th Edition, pag. 404
Incorrect
PMBOK Guide 5th Edition, pag. 404
-
Question 9 of 20
9. Question
Interpersonal skills include:
Correct
PMBOK Guide 5th Edition pag.407
Incorrect
PMBOK Guide 5th Edition pag.407
-
Question 10 of 20
10. Question
The process of communicating and working with the stakeholders is:
Correct
PMBOK Guide 5th Edition pag. 404
Incorrect
PMBOK Guide 5th Edition pag. 404
-
Question 11 of 20
11. Question
The process of monitoring OVERALL project stakeholder relationships is:
Correct
PMBOK Guide 5th Edition pag. 409
Incorrect
PMBOK Guide 5th Edition pag. 409
-
Question 12 of 20
12. Question
Cost-benefit analysis is a tool and technique of what process?
Correct
PMBOK Guide 5th Edition pag. 235
Incorrect
PMBOK Guide 5th Edition pag. 235
-
Question 13 of 20
13. Question
The PMO has just rolled out a project management methodology that has been tested and proven on a very large successful projects. They provide support and require compliance to this methodology. Your PMO is best described as:
Correct
PMBOK Guide 5th Edition pag. 11
Incorrect
PMBOK Guide 5th Edition pag. 11
-
Question 14 of 20
14. Question
You are working for a big project which consists of building a nuclear plant. During monitoring and controlling the project you have noticed that you have too much waiting time between some technical activities which is not necessary and the team members are moving more than is required to perform their responsibilities. More than that you waste time doing a specific testing over and over manually in order to minimize human error even you know that there is a automate tool which can do this faster and cheaper. So you started to think about eliminating all this kind of waste so you propose a quality improvement initiative based on:
Correct
Lean Six Sigma – it is a methodology that relies on a collaborative team effort to improve performance by systematically removing waste; combining lean manufacturing/lean enterprise and Six Sigma to eliminate the eight kinds of waste (muda): Time, Inventory, Motion, Waiting, Over production, Over processing, Defects, and Skills (abbreviated as ‘TIMWOODS’).
Incorrect
Lean Six Sigma – it is a methodology that relies on a collaborative team effort to improve performance by systematically removing waste; combining lean manufacturing/lean enterprise and Six Sigma to eliminate the eight kinds of waste (muda): Time, Inventory, Motion, Waiting, Over production, Over processing, Defects, and Skills (abbreviated as ‘TIMWOODS’).
-
Question 15 of 20
15. Question
Your company has chose to embrace a just in time approach within the organization, both on operations and projects. A new method was implemented for managing knowledge work with an emphasis on just-in-time delivery while not overloading the team members and new vocabulary was adopted: “backlog”, “board” etc. Most likely this method is:
Correct
Incorrect
Kanban
-
Question 16 of 20
16. Question
Commonly used process improvement models include:
Correct
PMBOK Guide 5th Edition, pag. 229
Incorrect
PMBOK Guide 5th Edition, pag. 229
-
Question 17 of 20
17. Question
You should provide weekly data and information to the PMO for feeding with actuals the existing corporate measurement system. Most likely this measurement system is:
Correct
PMBOK Guide 5th Edition pag. 11
Incorrect
PMBOK Guide 5th Edition pag. 11
-
Question 18 of 20
18. Question
You are conducting together with the quality assurance department a quality audit to verify compliance in the seller’s work processes so you are following the process:
Correct
Control procurements – PMBOK Guide 5th Edition pag. 383
Incorrect
Control procurements – PMBOK Guide 5th Edition pag. 383
-
Question 19 of 20
19. Question
You are a project manager and from this position you have a dispute with the seller technical expert regarding the scope of work. The dispute is still on the table even you have officially met the seller representatives trying to solve this claim. Considering that you think the claim is not a big issue and the financial impact of this dispute can be covered by the project reserve, how you should handle this dispute:
Correct
In accordance with alternative dispute resolution – PMBOK Guide 5th Edition pag. 384
Incorrect
In accordance with alternative dispute resolution – PMBOK Guide 5th Edition pag. 384
-
Question 20 of 20
20. Question
The CPI is 0.8 and The SPI is 0.9. The customer is challenging you with a lot of change requests. The sponsor is not very happy how the information is covered by the reports. All these are happening even all the team members are multitasking and ambitious and are characterized by a high entrepreneurial profile. They are most likely part of which generation:
Correct
Incorrect