Daca citim impresiile de la examen impartasite de cei care au obtinut deja certificarea PMP®, observam ca EVM (Earned Value Management) este una din cele mai prezente T&T in examen. Numarul de intrebari din examen poate varia intre 3-4 si 10, ceea ce pentru o singura tehnica este destul de mult. Insa cu certitudine sunt puncte nu foarte greu de obtinut in contextul in care notiunile, logica, formulele si limitarile EVM sunt intelese. Iata mai jos un test de 15 intrebari care le adreseaza.
Note:
1. Din momentul in care dati click pe “Start quiz” aveti 20 de minute pentru a finaliza testul.
2. Ca sa puteti rula testul va trebui sa aveti un user deja sau puteti sa va inregistrati acum si sa fiti logati.
3. Pentru a consulta raspunsurile corecte va trebui sa selectati dupa ce terminati testul optiunea:”View questions”
4. Pentru a afla rezultatul la test va trebui sa selectati “Finish Quiz”
5. Pentru discutii, comentarii sau debriefing Leave a reply
Quiz-summary
0 of 15 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
Information
_________
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 15 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
| Average score |
|
| Your score |
|
Categories
- Not categorized 0%
-
Referinte:
- Lista cu Formule
- TCPI
- PMBOK® Guide 6th Edition pag. 261-266
Pentru mai multe detalii sau daca doriti justificarea unui anumit raspuns Leave a reply.
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- Answered
- Review
-
Question 1 of 15
1. Question
You are the project manager of Transilvania highway project in which a total of 100 km are to be build over 10 months (10 km per month). The total budget for the Transilvania highway project is 1,000,000 RON. The project is now at the end of the 9th month. The Actual Cost is 500,000 RON and the Earned Value is 250,000 RON. You calculate estimate to complete (ETC) to 750,000 RON by doing bottom-up sum of all future costs. The Estimate at Completion (EAC) is:
Correct
Incorrect
-
Question 2 of 15
2. Question
The schedule variance expresses the variance between:
Correct
Incorrect
-
Question 3 of 15
3. Question
The cost performance index shows:
Correct
Incorrect
-
Question 4 of 15
4. Question
If your project is running on budget, your CPI will be:
Correct
Incorrect
-
Question 5 of 15
5. Question
Your project is running with a CV of 1,200 RON. The CPI is 1.1. The EAC is 100,000 RON. What is the BAC if the variance is typical?
Correct
Incorrect
-
Question 6 of 15
6. Question
Your CPI = 1.1 and your SPI = 0.9. How is your project doing?
Correct
Incorrect
-
Question 7 of 15
7. Question
EAC = BAC/CPI is the equation used for estimate at completion when:
Correct
Incorrect
-
Question 8 of 15
8. Question
Your project work is expected to be constant for the six month length of the project. During each month your budget is 10,000 RON. At the end of month four you have 40% of the total work complete and you have spent 60% of your total budget. The budget at completion for the project is:
Correct
Incorrect
-
Question 9 of 15
9. Question
A project has a value of the work done of 20,000 RON, actual cost = 35,000 RON and budgeted cost of work scheduled = 40,000 RON. The overall project budget is 100,000 RON. Assume that you will continue to spend at the same rate as you are currently spending. What is the variance at completion?
Correct
Incorrect
-
Question 10 of 15
10. Question
EAC = AC + (BAC-EV) is the equation used for estimate at completion when:
Correct
Incorrect
-
Question 11 of 15
11. Question
You are the project manager of Transilvania highway project in which a total of 100 km are to be build over 10 months (10 km per month). The total budget for the Transilvania highway project is 1,000,000 RON. The project is now at the end of the 9th month with 50 km built and 500,000 RON spent. The project is behind schedule owing to a work strike. A potential problem caused by the main supplier is ready to impact the future costs with 30%. The Cost Performance Index for the project is:
Correct
Incorrect
-
Question 12 of 15
12. Question
A project has a earned value of 20,000 RON, actual cost = 35,000 RON and a planned value = 40,000 RON. The overall project budget is 100,000 RON. Assuming the remaining work will be impacted by the current cost performance and by a schedule performance index of 0.7, what is the Estimate At Completion (EAC) of the project?
Correct
Incorrect
-
Question 13 of 15
13. Question
Another project has Actual Cost (AC) = 500k RON, Planned Value (PV) = 600K RON and Earned Value (EV) = 400k RON. If the Budget at Completion (BAC) for your project is 1,000k RON and the variance is atypical the Estimate at Completion (EAC) is:
Correct
Incorrect
The EV, AC and PV provided in the question are for ANOTHER project. So for yout project you only have the BAC and the information that the variance is atypycal but no information about EV and AC.
-
Question 14 of 15
14. Question
Your project has an earned value of 20,000 RON. Your sunk costs are 35,000 RON. The budgeted cost for work scheduled is 40,000 RON. The overall project budget is 100,000 RON. Assuming the variance is typical and the SPI will influence remaining work, what is the Estimate At Completion (EAC) of the project?
Correct
Incorrect
-
Question 15 of 15
15. Question
A project is estimated to cost 100,000 RON with a timeline of 100 days. After 40 days, the project manager finds that 40% of the project is complete and Actual costs are 50,000 RON. What is the Cost Performance Index (CPI)?
Correct
Incorrect

by
Salut,
La intrebarea 1 avem enuntul dar, lipseste intrebarea. 😀
Multumesc,
Alex.
Salut Alex,
Multumesc pentru atentionare. Corectat. “The Estimate at Completion (EAC) is:”