Anul 2021 a adus mai multe schimbari la examenul de PMP®. O sinteza a schimbarilor poate fi urmarita aici:
Printre schimbarile la examen se numara si introducerea unor noi categorii de intrebari pe langa cele clasice, cu un singur raspuns corect. Aceste categorii noi adaugate sunt:
- Multiple correct answers;
- Matching Drag & Drop;
- Fill in the blank;
- Hotspot questions;
Pentru cei care doresc sa exerseze, iata mai jos un test free de 15 intrebari care se incadreaza in categoria intrebarilor care au mai mult de un raspuns corect (Multiple correct answers):
Note:
1. Din momentul in care dati click pe “Start quiz” aveti 19 minute pentru a finaliza testul.
2. Ca sa puteti rula testul va trebui sa aveti un user deja sau puteti sa va inregistrati acum si sa fiti logati.
3. Pentru a consulta raspunsurile corecte va trebui sa selectati dupa ce terminati testul optiunea:”View questions”
4. Pentru a afla rezultatul la test va trebui sa selectati “Finish Quiz”
5. Pentru discutii, comentarii sau debriefing Leave a reply
Quiz-summary
0 of 15 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
Information
_________
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 15 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Average score |
|
Your score |
|
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- Answered
- Review
-
Question 1 of 15
1. Question
Feature-Driven Development (FDD) was developed to meet the specific needs of a large software development project. Features relate to a small business value capability. There are six primary roles on a Feature-Driven Development project where individuals can take on one or more of the following roles (choose six):
Correct
See Agile Practice Guide pag. 108
Incorrect
See Agile Practice Guide pag. 108
-
Question 2 of 15
2. Question
Disciplined Agile (DA) principles are (choose 6):
Correct
Agile Practice Guide pag. 114
Incorrect
Agile Practice Guide pag. 114
-
Question 3 of 15
3. Question
The iterative, incremental, and agile approaches work well for projects that (choose three):
Correct
Agile Practice Guide pag. 16
Incorrect
Agile Practice Guide pag. 16
-
Question 4 of 15
4. Question
Which of the following are tools to Plan Quality Management? (choose two)
Correct
PMBOK Guide 6th ed. pag. 281
Incorrect
PMBOK Guide 6th ed. pag. 281
-
Question 5 of 15
5. Question
A project manager is developing a quality management plan for a project to build a custom industrial stamping machine. The machine will be assembled from parts produced by vendors. To determine the cost of quality, the project manager examines the costs of conformance and nonconformance. Which of the following should the project manager review to determine the cost of conformance? (Choose four)
Correct
PMBOK Guide 6th ed. pag. 283
Incorrect
PMBOK Guide 6th ed. pag. 283
-
Question 6 of 15
6. Question
An organization has established a controlling project management office. The first task of the PMO is to update the guidelines for project compliance in the organization. Which of the following the PMO enforce (choose three)
Correct
PMBOK Guide 6th ed. pag. 48-49, 710
Incorrect
PMBOK Guide 6th ed. pag. 48-49, 710
-
Question 7 of 15
7. Question
You are managing a project team that has recently expanded by new team members working remotely from another country. Their roles have been outlined to form a preliminary team charter. Nevertheless, you have noticed a considerable lack of acceptance of cultural differences in the team, resulting in frequent conflicts. Which of the following techniques could help you in this situation? (choose three)
Correct
PMBOK Guide 6th. edition pag. 340-342, 348
Incorrect
PMBOK Guide 6th. edition pag. 340-342, 348
-
Question 8 of 15
8. Question
During project execution, a key stakeholder leaves the company and a new stakeholder is coming on board. The project manager understands that the stakeholder enagement plan should be updated to reflect the strategies and actions required to involve the new stakeholder in the project. The project manager meets with the new stakeholder for an interview. Which of the following questions would be the most helpful for the project manager in updating the plan? (choose three)
Correct
PMBOK Guide 6th ed. pag. 516 – 522
Incorrect
PMBOK Guide 6th ed. pag. 516 – 522
-
Question 9 of 15
9. Question
The latest software released to the customer in the first project phase is full of defects. The customer is upset and demands that the development of the new release, which is planned to be delivered in the second phase, to be much more transparent. The customer wants to see the team’s results more regularly and without very long development intervals in-between. Which of the following could the project team introduce in the second phase to better comply with the customer’s demand? (choose four)
Correct
PMBOK Guide 6th ed. page 177 and Agile Practice Guide pag 32-33, 56
Incorrect
PMBOK Guide 6th ed. page 177 and Agile Practice Guide pag 32-33, 56
-
Question 10 of 15
10. Question
You was appointed as project manager for building an application which will automate 60% of HR processes, but you should clarify with the customer some requirements. Which of the following techniques is most likely to use? (choose three)
Correct
PMBOK Guide 6th ed. pag. 142
Incorrect
PMBOK Guide 6th ed. pag. 142
-
Question 11 of 15
11. Question
During a status meeting you find out about a conflict between two stakeholders of your project. You want to address this conflict but you know that your resolution method is influenced by the following factors: (choose three)
Correct
PMBOK Guide 6th ed. pag. 348
Incorrect
PMBOK Guide 6th ed. pag. 348
-
Question 12 of 15
12. Question
As the project progresses and deliverables are being produced, the project manager revisits the stakeholder engagement plan to determine what refinements can be made to the plan to improve stakeholder engagement. Among he project documents, which will be the most influential to the project management process being performed? (choose three)
Correct
PMBOK Guide 6th ed.pag.89, 519
Incorrect
PMBOK Guide 6th ed.pag.89, 519
-
Question 13 of 15
13. Question
You noticed that there are a lot of misunderstandings in the emails the team-members exchange. Which of the following rules should be used in order to reduce the misunderstandings? (choose five)
Correct
PMBOK Guide 6th ed. pag. 363
Incorrect
PMBOK Guide 6th ed. pag. 363
-
Question 14 of 15
14. Question
A scrum master has been hired to lead a project for an organization that has no prior experience with agile methodologies. The project will use Scrumban for the development of the project deliverables. Which of the following training activities will be critical for the success of the project? (choose three)
Correct
PMBOK Guide 6th ed. pag. 342 and Agile Practice Guide 32,41,52,101, 103-105,108
Incorrect
PMBOK Guide 6th ed. pag. 342 and Agile Practice Guide 32,41,52,101, 103-105,108
-
Question 15 of 15
15. Question
Your organization is creating an agile environment but you know that the attributes of succesful agile team are: (choose five)
Correct
Agile Practice Guide pag. 40
Incorrect
Agile Practice Guide pag. 40
Difficulty level: Medium-High