Sunt mult intrebari in examenul PMI-ACP care vizeaza pe langa cunostintele teoretice si experienta voastra, felul cum ati trait lucrurile in practica proiectelor agile pe care le-ati desfasurat.
Testul de mai jos combina intrebari cu raspuns teoretic, care tin de definitiile unor tehnici sau metode, cu intrebari cu un grad mai mare de dificultate, care va testeaza experienta.
Note:
1. Din momentul in care dati click pe “Start quiz” aveti 30 de minute pentru a finaliza testul.
2. Ca sa puteti rula testul va trebui sa aveti un user deja sau puteti sa va inregistrati acum si sa fiti logati.
3. Pentru a consulta raspunsurile corecte va trebui sa selectati dupa ce terminati testul optiunea:”View questions”
4. Pentru a afla rezultatul la test va trebui sa selectati “Finish Quiz”
5. Pentru discutii, comentarii sau debriefing Leave a reply
Quiz-summary
0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
_________
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 20 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
| Average score |
|
| Your score |
|
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Which way do agile project teams address the risk of having insufficient information at the beginning of the project?
Correct
Incorrect
-
Question 2 of 20
2. Question
To what extent does an agile development team gets to be self-organized?
Correct
Incorrect
-
Question 3 of 20
3. Question
Please indicate something that is not an attribution of the ScrumMaster
Correct
Incorrect
-
Question 4 of 20
4. Question
In a Lean software development environment, what is the name of the practice associated with delaying the decisions that can limit the team’s options, up until the last possible moment?
Correct
Incorrect
-
Question 5 of 20
5. Question
Which method is better than Payback Period for assessing financial feasibility of a project, as it assumes the value of money is degrading over time and it follows the financial results even after the initial costs are covered?
Correct
Incorrect
-
Question 6 of 20
6. Question
While looking at their current way for developing products, a team is using a tool to help them analyze and design their Information flow in the development process. Which tool are they most likely using?
Correct
Incorrect
-
Question 7 of 20
7. Question
The main purpose for a team to use daily meetings with all team members committing to resolve tasks throughout the day and uncovering blocking issues, is to:
Correct
Incorrect
-
Question 8 of 20
8. Question
Right after integrating her new work in the common repository, Jane determines some functional issue has appeared in an area of the product that she hadn’t specifically addressed with her work. Who needs to address the issue?
Correct
Incorrect
-
Question 9 of 20
9. Question
The team elicits requirements from stakeholder groups, breaks them down into stories and ranks the stories, then pulls the prioritized requirements into the development process. By doing this which process is the team using?
Correct
Incorrect
-
Question 10 of 20
10. Question
The estimates for a software project move from a very broad range early in the life cycle of the project to more manageable ranges when the scope and specifications are understood and then continue to narrow as the team learns more about the project. Why should agile teams use estimate ranges instead of single-point estimates, as the project progresses?
Correct
Incorrect
-
Question 11 of 20
11. Question
The cost for closing the gap between the cost of change of a product or feature and the optimal cost of change for that product or feature, is known as:
Correct
Incorrect
-
Question 12 of 20
12. Question
In a team retrospective meeting, the continuous improvement process is done when:
Correct
Incorrect
-
Question 13 of 20
13. Question
An agile team is using Fishbone analysis as a tool to determine the most likely causes that led to an undesired effect. In doing so, which is NOT a concern for the team?
Correct
Incorrect
-
Question 14 of 20
14. Question
Using Fist-of-Five voting, the team has reached a decision by indicating their agreement or disagreement on a gradual scale, then reached a decision in a participatory manner. To which agile value pair do they show commitment by doing so?
Correct
Incorrect
-
Question 15 of 20
15. Question
Measuring cycle times, work in process and likely completion dates can be achieved using which agile reporting tool?
Correct
Incorrect
-
Question 16 of 20
16. Question
The agile value proposition is to address project risk as soon as possible. How is this achieved from product features prioritization perspective?
Correct
Incorrect
-
Question 17 of 20
17. Question
The benefit of having early discussions and collaboration with the entire team and the stakeholders is achieved by building together which form of scope planning tool?
Correct
Incorrect
-
Question 18 of 20
18. Question
How is Susan, as an agile coach, expected to help the team better resolve the quality issues that they are facing?
Correct
Incorrect
-
Question 19 of 20
19. Question
An agile project is benefiting the most from the knowledge and skills that its business representative has accumulated, by having him/her located:
Correct
Incorrect
-
Question 20 of 20
20. Question
The Kanban method used in product development is limiting WIP by:
Correct
Incorrect

Nice questions but not so hard as I expected and really useful for my preparation.
I am impressed by my result but I can say that I was really focused and concentrated.
Thank you, Razvan. You have a similar test here: https://www.bryx.ro/2017/11/schimbari-lexicale-la-examenul-pmi-acp-si-un-nou-test-de-20-de-intrebari/